Imperial bumps up cost of Kearl oil sands project

A giant piece of Imperial’s Kearl oil sands project. The delay in transporting such equipment resulted from a battle Imperial Oil lost in Idaho and Montana, where residents urged local officials to reject the company’s plans to move enormous, South Korean-made pieces of the Kearl project on their highways.

Barry Kough/ASSOCIATED PRESS

Imperial Oil Ltd. boosted the price tag of its Kearl oil sands mine by $2-billion, the second major increase for the project and the latest cost increase to hit Alberta's energy industry.

Imperial said Kearl's first development phase will cost $12.9-billion, up from $10.9-billion estimated previously. And the latest estimate is 61-per-cent higher than the original calculation of $8-billion.

The energy company's latest financial setback is tied to delays in transporting equipment for the project, and the harsh winter in northern Alberta further slowed development.

Story continues below advertisement

Now some analysts are concerned Kearl could miss its expected production start this quarter.

Kearl's escalating budget is another indication of the difficulties facing the oil sands sector, which is grappling with higher costs for materials and labour, as well as discounted prices for heavy crude due to an oversupply caused by transportation bottlenecks – mainly pipelines – for exported oil.

Companies are reconsidering planned projects, as the industry re-calibrates spending to boost results that have often failed to impress investors. Suncor Energy Inc., for example, is weighing how and when to proceed with three undeveloped projects. It also withdrew its goal of hitting production of 1 million barrels of oil per day by 2020.

Imperial Oil, controlled by Exxon Mobil Corp., expects Kearl to produce its first drops of bitumen this quarter. This timeline has been pushed back before, and doubts remain about the current target. "We would not be surprised to see production not starting up until May," said Andrew Potter, an analyst at CIBC World Markets Inc.

"The bigger impact will likely be to the [Imperial/Exxon] reputation as a 'premium' operator," Mr. Potter said in a research note.

The delay in transporting equipment resulted from a battle Imperial Oil lost in Idaho and Montana, where residents urged local officials to reject the company's plans to move enormous, South Korean-made pieces of the Kearl project on their highways. Critics focused on traffic delays, as well as environmental concerns.

Imperial had to take more than 200 of the modules apart so they could be moved on an alternate route. They were later reassembled, a process which required hundreds of people. This pushed up costs and delayed the project, even though the company was previously adamant the damage would not be severe.

Story continues below advertisement

Imperial on Friday said it will now cost $6.80 per barrel to develop the first and second phase of the project. That is a 10-per-cent increase from its last estimate of $6.20 per barrel. The company originally predicted it would cost $5 per barrel.

Imperial still expects a second phase of Kearl to ring in at $8.9-billion, despite revisions to the first phase of the project. It has not released a cost estimate for the final phase of the project, known as "de-bottlenecking," but it expects the development costs per barrel to be the same as the during first two phases.

This means the cost of the entire project will reach about $31.2-billion, the company confirmed. The Kearl mine is expected to produce 345,000 barrels of bitumen per day by 2020, when it is running at full speed.

Imperial reported a profit of $1.07-billion in the fourth quarter, or $1.26 per share, compared to $1-billion or $1.18 per share in the final quarter of 2011. The company's downstream businesses, such as refining, were the brightest spot, posting a profit of $549-million, a record quarterly showing, Imperial said.

Report an error Licensing Options
About the Author

Carrie Tait joined the Globe in January, 2011, mainly reporting on energy from the Calgary bureau. Previously, she spent six years working for the National Post in both Calgary and Toronto. She has a master’s degree in journalism from the University of Western Ontario and a bachelor’s degree in political studies from the University of Saskatchewan. More

Comments

The Globe invites you to share your views. Please stay on topic and be respectful to everyone. For more information on our commenting policies and how our community-based moderation works, please read our Community Guidelines and our Terms and Conditions.

We’ve made some technical updates to our commenting software. If you are experiencing any issues posting comments, simply log out and log back in.

Discussion loading… ✨

Combined Shape Created with Sketch.

Combined Shape Created with Sketch.

Thank you!

You are now subscribed to the newsletter at

You can unsubscribe from this newsletter or Globe promotions at any time by clicking the link at the bottom of the newsletter, or by emailing us at privacy@globeandmail.com.