Newfoundland and Labrador Hydro has promised to add generating capacity and improve its existing equipment to avoid the kind of rolling blackouts that plagued the province earlier this year.

But CEO Ed Martin says he can't guarantee that the power disruptions won't happen again.

An unusual cold snap in early January along with high winds and equipment malfunctions led to both planned and unexpected power failures across the island.

Story continues below advertisement

At one point, 190,000 electricity customers were without power.

Martin says the utility will add 100 megawatts of capacity to the grid on the Avalon Peninsula.

He says Newfoundland and Labrador Hydro will also overhaul some gas turbines, accelerate replacement of 230 electric breakers and there are plans to give the public more notice in case there are more blackouts.

Martin submitted a report to the province's Public Utilities Board on Monday, saying the outages did not have a root cause.

Instead, he says there was a series of unplanned events that are unlikely to occur again.

Report an error
Comments

The Globe invites you to share your views. Please stay on topic and be respectful to everyone. For more information on our commenting policies and how our community-based moderation works, please read our Community Guidelines and our Terms and Conditions.

We’ve made some technical updates to our commenting software. If you are experiencing any issues posting comments, simply log out and log back in.

Discussion loading… ✨