Six facilities in Toronto, Milton, Markham and Hamilton are months behind schedule. Read our full look into the delays here.
CIBC Pan Am/ Parapan Am Aquatics Centre and Field House
Events: Aquatics, fencing, modern pentathlon
Location: University of Toronto Scarborough, Toronto
Cost: $205,123,855
Target completion date preconstruction: July, 2014
Completed: September, 2014
CIBC Hamilton Pan Am Soccer Stadium
Events: Soccer
Location: Balsam Avenue North, Hamilton
Cost: $145,667,589
Target completion date preconstruction: End of June 2014
New completion date: Fall 2014
Atos Markham Pan Am/Parapan Am Centre
Events: Badminton, table tennis, water polo
Location: 16 Main St., Markham
Cost: $78,518,000
Target completion date preconstruction: July, 2014
New completion date: Fall 2014
Cisco Milton Pan Am/Parapan Am Velodrome
Events: Track cycling
Location: Tremaine Road and Louis St. Laurent Boulevard, Milton
Cost: $56-million
Target completion date preconstruction: September, 2014
New completion date: Before Christmas 2014
CIBC Pan Am/ Parapan Am Athletics Stadium
Events: Athletics
Location: York University, Toronto
Cost: $45,450,000
Target completion date preconstruction: September, 2014
New completion date: Fall 2014
Etobicoke Olympium
Events: Aquatics training
Location: 590 Rathburn Rd., Toronto
Cost: $20-million
Target completion date preconstruction: July, 2014
New completion date: Fall 2014