Bombardier Inc.'s behind-schedule C Series new-jet program faces possible further delays and ballooning costs given how little has been done so far in the flight-test phase, says one analyst.

The C Series' revised 22-to-23-month flight-test plan is similar to the 21 months Boeing Co. took to certify its 787 but "actual progress through the first four months of C Series flight-testing is well behind Boeing's early pace on 787," UBS Securities analyst Darryl Genovesi says in a research report published Monday.

Montreal-based Bombardier will likely burn through cash at $1.48-billion (U.S.) in 2014 and $1-billion next year, $1-billion worse than the combined 2014-2015 outflow previously modeled at UBS, he said.

Story continues below advertisement

The anticipated increase is mainly due to an extra $500-million cost in C Series development and $400-million in inventory build to support the production ramp-up, said Mr. Genovesi.

Free cash flow break-even in 2016 is possible, but "we think cash likely remains negative for longer if C Series schedule slips again."

Bombardier Commercial Aircraft spokesman Marc Duchesne said the company is comfortable with its new deadline of entry-into-service in the second half of 2015.

"This new timeline was revised by the C Series leadership team, the Bombardier Aerospace leadership team and the Bombardier Inc. leadership team," he said in an interview.

He declined to comment on the specifics of the UBS report.

"This isn't the first time we launch a plane," he said, referring to the more than two dozen new aircraft – including the popular regional jet – Bombardier has brought onto the market over the past three decades.

Bombardier is betting big on the success of the C Series and new business jets, but has experienced several delays on both the C Series and some business-jet programs.

Story continues below advertisement

The aerospace giant said on Jan. 16 it is once again delaying the aircraft's entry into service, until late next year instead of fall 2014 due to adjustments in flight testing.

Bombardier president and chief executive officer Pierre Beaudoin said in Davos last week at the World Economic Forum that the company won't need to raise additional funding this year after delaying the C Series for a fourth time.

The cost of the C Series development program is now pegged at about $3.9-billion.

Also last week, Bombardier Aerospace said it is slashing 1,700 jobs as part of a cost-containment program, but said the cuts are not directly related to any one program.

UBS analyst Mr. Genovesi also said in his report that he continues to anticipate that Bombardier will push out or retract its 2014 targets for a $500-million development spending decline and 8-per-cent margins at both its aerospace and rail divisions.

The decline in the value of the Canadian dollar will provide Bombardier Aerospace with some breathing room, "but we still think it's unlikely that [Bombardier] can get to 8 per cent in 2014 without a sharp bizjet market recovery."

Story continues below advertisement

Report an error Licensing Options
About the Author
Quebec Business Correspondent

Bertrand has been covering Quebec business and finance since 2000. Before joining The Globe and Mail in 2000, he was the Toronto-based national business correspondent for Southam News. He has a B.A. from McGill University and a Bachelor of Applied Arts from Ryerson. More

Comments

The Globe invites you to share your views. Please stay on topic and be respectful to everyone. For more information on our commenting policies and how our community-based moderation works, please read our Community Guidelines and our Terms and Conditions.

We’ve made some technical updates to our commenting software. If you are experiencing any issues posting comments, simply log out and log back in.

Discussion loading… ✨

Combined Shape Created with Sketch.

Combined Shape Created with Sketch.

Thank you!

You are now subscribed to the newsletter at

You can unsubscribe from this newsletter or Globe promotions at any time by clicking the link at the bottom of the newsletter, or by emailing us at privacy@globeandmail.com.